Ningxia Baofeng olefins project is progressing well

January 16, in the Ningxia Baofeng Energy Group Limited olefins project 300,000 tons / year polyethylene unit at the installation site, the construction of China National Chemical Engineering Co., Ltd. successfully completed the fourth polymerization reactor lifting. Washi tape

The station polymerization discouraged 444 tons, 41.98 meters high, is the largest piece of equipment throughout the polyethylene unit, also the most difficult to install a piece of equipment. In order to ensure a smooth overweight large equipment lifting these units successfully, the four modernizations construction company construction workers carefully designed by a 400-ton crawler crane main crane,Masking tape

 a 350-tonne crawler crane tail slide program, a smooth and accurate these pieces NTU hoisting equipment. Wholesale masking tape